Consolidated Computational Research Facility (CCRF) & Chiller Plant, National Institutes of Health/Rocky Mountain Laboratories
Project Description: This project is renovation work to implement a new consolidated Data and Computation Center. New mechanical systems designed and constructed include a bi-directional fault-tolerant chilled water distribution system teamed with in-row type chilled water cooling units situated on the raised Data Floor. Also included are new heat exchangers, redundant chilled water pumps, chilled water storage tanks and controls, along with a local low-ambient emergency air-cooled chiller to support the Data Center. Electrical work includes a new building electrical service, and redundant electrical distribution system for the Data Center. The new electrical system includes interior and exterior distribution gear, automatic transfer switches, power transformers, and un-interruptible power supplies. Special systems include fire Alarm, access control, video surveillance, and a paging system.
Project Budget: $10,000,000
Building Area: 5,300 SF